Invitation for Bid: Fairview Demolition - 26 Buildings (IFB-FD 10-2026)

For a printable version of the Invitation for Bid: Fairview Demolition - 26 Buildings (IFB-FD 10-2026), which includes all content as listed below, click here.


FAIRVIEW DEMOLITION,
(26 BUILDINGS)

Invitation for Bid (IFB)


IFB Number: IFB-FD 10-2026
Issue Date: October 23, 2026
Bid Opening Date/Time: November 23, 2026 at 2:00 P.M. EST
Bid Opening Location: *Keystone Development Building - 1212 E. Watauga Avenue, Johnson City, TN 37601

Pre-Bid Conference: November 4, 2026 at 2:00 P.M. EST
Please read this document prior to the meeting.
Attendance is not mandatory but recommended.

Pre-Bid Location: *Keystone Development Building - 1212 E. Watauga Avenue, Johnson City, TN 37601

Availability and Award Results: The IFB documents are posted and available at JCHA's webpage at: www.jchousing.org 
Award results will also be posted at conclusion of IFB process.

*Keystone Development Inc. is a nonprofit organization established by the Johnson City Housing Authority.


SECTION 1 - IFB COVER LETTER

Sealed Bids for: IFB: Fairview Demolition (26 Buildings)

Will be received at the following address:

Johnson City Housing Authority (Keystone Dev. Bldg.)
1212 E. Watauga Avenue
Johnson City, TN 37601

until 2:00 p.m. EST, on November 23, 2026. Bids shall be presented on the form prescribed by the Housing Authority, be enclosed in a sealed envelope clearly displaying the Outer Bid Envelope Information Page as provided in the Bid Documents, and subject to the General Conditions, Terms, and Specifications as contained in the Bid Documents. All Bids received by the deadline, will be publicly opened, read aloud, and recorded at 2:00 p.m. on November 23, 2026.

A Pre-Bid Conference and site visit will be held at 2:00 pm. EST November 4, 2026 at the offices of the Johnson City Housing Authority (Keystone Dev. Bldg.), 1212 E. Watauga Avenue, Johnson City, TN 37601.

By submission of a Bid, the bidder agrees, if its Bid is accepted, to enter into a Contract with the Housing Authority for the Contract Price and within the Contract Time indicated in the attached IFB. The bidder further accepts all of the terms and conditions of the IFB.

The IFB must be independently arrived at and be prepared in accordance with the bid documents. In addition, the HUD-required Representations and Certifications (Form HUD-5369-A) must be completed, dated, and signed by the bidder or an authorized representative.

The bid prices shall be included as provided in the attached IFB. All prices shall be on a firm-fixed-price basis and are not subject to adjustment based on costs incurred (base bid and non-base bid). The Housing Authority reserves the right to reject any and/or all bids.

Bidders should be advised that, prior to award of any contract, the Housing Authority reserves the right to conduct a pre-award survey for the purpose of determining the bidder's responsibleness and capacity to perform the contract. This survey may include, but is not necessarily limited to, a review of subcontracting agreements, financial capacity, and quality of work performed on other contracts.

All bidders must be licensed Contractors in the State of Tennessee as required by the Contractors' Licensing Act of 1994 (TCA Title 62), as revised and as applicable.

Bid, payment and performance bonds are required IF the total bid exceeds $100,000.

  • A bid bond made payable to the Johnson City Housing Authority in the amount of 5% of the total Bid price, (if bid exceeds $100,000).
  • Performance and payment bonds for 100% of the contract price for the successful bidder, (if contract exceeds $100,000).
  • All bonding companies must be listed in the "Federal Register, Department of the Treasury Fiscal Service, Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies; Notice". Companies licensed to do business in the state of Tennessee must issue all required bonds.

All bids must be signed and dated; if a joint venture is submitting the bid, each joint venturer must sign the bid.

Addendums (if applicable) will be posted at JCHA's website. It is the responsibility of the entity submitting a bid and/or proposal to obtain posted Addendum and check appropriate box on "Section 2 Bid/Price Form".

Bid Documents may be obtained at JCHA's administrative office, or at JCHA's website. Questions regarding the IFB are to be submitted no later than 4:30 PM on November 12, 2026 in writing, including email to [email protected].

Sam Edwards
CEO/Executive Director


SECTION 2 - BID / PRICE FORM (RETURN WITH BID)
PROJECT: IFB: Fairview Demolition (26 Buildings, Site Map Attached) 

For the Bid / Price Form that must be returned with the bid, please contact us or pick up a copy at our office main office located at 901 Pardee St, Johnson City, TN 37601, during regular office hours.


SECTION 3 - SPECIFICATIONS

  1. The work project is the demolition of 26 buildings in the Fairview Development. The work included under these specifications, consist of providing all items, articles and materials, specified herein, including all labor, materials, services, equipment, and incidentals necessary for the completion of the work, unless noted otherwise. The location involves the following streets: E. Fairview Ave., E. Myrtle Ave. Circle Court, E. Watauga Ave. and Steel Street. The point of reference will be 504 Steel Street, Johnson City, TN. 37601. NOTE: JCHA has already conducted comprehensive pre-demolition asbestos sampling for select units in accordance with National Emissions Standard for Hazard Air Pollutants (NESHAP) with the survey sampling showing no asbestos present.
  2. Contractor to inspect the site for its character and the type of structures to be demolished prior to bid. The Housing Authority assumes no responsibility for the condition of existing buildings, structures, etc. within the demolition area.
  3. The buildings are primarily brick with concrete slabs.
  4. The work shall be completed no later than 75 calendar days after Notice to Proceed.
  5. Work schedule to be approved by Housing Authority.
  6. Dispose of applicable demolition debris in an approved landfill and in accordance with all regulations. All demolition fees are to be paid by contractor. Housing Authority dumpsters shall not be used.
  7. Contractor to have the proper license and is responsible for the proper licenses, fees, and permits required to conduct work as applicable.
  8. Contractor to comply with all applicable federal, state, and local regulations.
  9. Contractor to comply with such standards as noted by OSHA/TOSHA or any other applicable agency.
  10. Contractor to comply with City of Johnson City, TN. Development Services "Clearance of Utilities for Demolition-Policies Agreement" and be responsible for all associated costs including decommissioning all necessary existing utilities prior to demolition. NOTE: JCHA has already completed the "cap-off" (disconnection) of water & sewer lines to buildings. Gas utilities have been abandoned. Electrical has been disconnected from most buildings and the
    remaining are underway.
  11. Contractor's company must perform work and may only subcontract to others with pre-approval from Housing Authority.
  12. Contractor will, in providing labor for the Project, comply with the provisions of the Tennessee Lawful Employment Act, including without limitation maintaining and making available for inspection by Owner, as they may deem necessary, appropriate Form l-9's for all employees assigned to the Project.
  13. Protect all adjacent areas from damage and construction dust. Clean, repair, or replace any disturbance or damage caused by construction operations to pre-existing conditions or better.
  14. Work to be conducted during normal business hours unless alternate schedule approved by Housing Authority.
  15. Conduct a basic grade level backfill and compaction at every demolished building site foundation hole with clean fill.
  16. Stabilize and seed the area after demolition as necessary and in accordance with City of Johnson City, TN. requirements.
  17. Contractor to be aware of potential concrete "piers" underneath slab during demolition. Past demolition of buildings at this site uncovered pier type concrete sections under slab. Contractor to include removal of existing slab and "piers" as part of the scope of work and include this scope of work as part of their base bid. Piers are noted in plans to be approximately 12" in diameter at top and 20" at bottom but may be slightly larger, (see following pages).

Building A - 8 Piers Noted

Blueprint Foundation Plan of Building A.

Building B - 13 Piers Noted

Blueprint Foundation Plan of Building B.

Building C - 16 Piers Noted

Blueprint Foundation Plan of Building C.

Building D - 19 Piers Noted

Blueprint Foundation Plan of Building D.

Building E (part 1) - 10 Piers Noted (7 round & 3 square)

Blueprint Foundation Plan of Building E.

Building E (part 2) - 3 Piers Noted, (round)

Blueprint Foundation Plan of Building E.

Building F - No Picture Available. Building is two-story with four apartment units. Assume up to 20 Piers. 

Concrete Piers. Appears to be approximately 2-3' deep. 

Concrete piers laying in dirt.


SECTION 4 - GENERAL CONDITIONS & SPECIAL CONDITIONS 

ARTICLE 1

Progress payments per an acceptable monthly pay request from the Contractor, less retainage of 5% as applicable, shall be made to the Contractor for Work satisfactorily performed no later than ten (10) days after receipt of application for payment or approved invoice for large scale and on-going projects. Contractor's Schedule of Values must be approved prior to submitting first Pay Request. Progress payments will not be applicable to work projects lasting less than one calendar month and to be billed after work completion as one lump sum, paid within "net 30" of approved invoice. These payments are subject to receipt for such lien waivers, affidavits, warranties and guarantees required by the Contract Documents or Contractor.

ARTICLE 2

SCHEDULE OF WORK. Time is of the essence. Contractor shall provide Owner with any requested scheduling information of Contractor's Work. The Schedule of Work, including that of this Contract shall be prepared by Owner and may be revised as the Work progresses. The schedule must be agreeable with
the Contractor. Contractor recognizes that changes may be made in the Schedule of Work and agrees to comply with such changes without additional compensation Contractor shall coordinate its work with all other contractors, subcontractors, and suppliers on the Project so as not to delay or damage their performance, work or the Project.

ARTICLE 3

CHANGES: Owner, without nullifying this Agreement, may direct Contractor in writing to make changes to Contractor's Work. Adjustment, if any, in the contract price or contract time resulting from such changes shall be set forth in a Contract Change Order pursuant to the Contract Documents.

ARTICLE 4

FAILURE OF PERFORMANCE. Should Contractor fail to satisfy contractual deficiencies within three (3) working days from receipt of Owner's written notice, then the Owner, without prejudice to any right or remedies, shall have the right to take whatever steps it deems necessary to correct said deficiencies and deduct cost from unpaid balance of subcontract amount.

ARTICLE 5

INSURANCE. The Contractor shall at all times indemnify and save the Owner harmless from all claims on this job and from any or all damage, loss or expense that may be incurred by the Owner by reason of any damage to its property or by reason of any injuries or death to its employees or third persons, or from any damage to the property that may be caused by or result from the performance of the work by the Contractor. Contractors shall purchase and maintain during the entire project and during the warranty period, insurance with the minimum limits and coverage shown below or greater (if required by the Contract Documents), from insurance companies acceptable to Owner - Johnson City Housing Authority.

GENERAL LIABILITY: Contractor shall carry standard ISO General Liability coverage, written on an occurrence basis - including Completed Operations. The coverage must be endorsed to name Owner - Johnson City Housing Authority (including the Architect and others as required in contract documents) as an "additional insured" providing "Your Work" coverage (i.e. ongoing operations and Completed Operations) "arising out of' work performed for the Owner by the Contractor. The "Additional Insured" form shall also state that this insurance shall be primary without right of contribution from any other insurance available to the "additional insureds".

The CGL must be written on an occurrence basis, with minimum limits of:

  • Each Occurrence $1,000,000
  • General Aggregate - Per Project $2,000,000
  • Products and Completed Operations Aggregate $1,000,000
  • Personal/Advertising Injury $1,000,000
  • Medical Payments $5,000

COMPREHENSIVE AUTOMOBILE LIABILITY on occurrence basis covering all Owned, Non-Owned and Hired Vehicles for limits of liability equal to $1 ,000,000 Combined Single Limit.

WORKER'S COMPENSATION including Occupations Disease insurance meeting the statutory requirements of the State in which work is to be performed together with a Broad Form All States Endorsement and containing Employer's Liability insurance in an amount of at least $100,000 Each Accident/ $500,000 Disease - Policy Limit/ $100,000 Disease - Each Employee. Workers Compensation shall waive the rights of subrogation in favor of all additional insureds.

A certificate of insurance form must be filed with Owner - Johnson City Housing Authority prior to the commencement of any work and must state coverage will not be altered, cancelled or allowed to expire without thirty (30) days written notice by certified mail to Owner - Johnson City Housing Authority If any of the above coverages are subject to or are in excess of any deductibles or self-retention, these amounts must be stated on the certificate, and said deductibles and self-retention will be the sole responsibility of Contractor.

It is understood and agreed that the insurance coverage and limits, required above, shall not limit the extent of Contractor's responsibilities and liabilities specified within Contract Documents or by law. It is understood and agreed that authorization is hereby granted to refuse entry to job site and to withhold
payments to Contractor until a properly executed Certificate of Insurance is received by Owner - Johnson City Housing Authority.

Contractor's Insurance Requirements set forth herein shall become and be part of any purchase order or contract issued by Owner - Johnson City Housing Authority to Contractor as though fully set forth in said purchase order or contract.

Should Contractor fail or neglect to provide the required insurance, Owner - Johnson City Housing Authority shall have the right, but not the duty, to provide such insurance and deduct from any money that may be due or become due to Contractor for any and all premium or costs Owner - Johnson City Housing Authority incurs. Equivalent insurance coverage must be obtained from each Subcontractor, if any, before permitting them on the site of the project. Otherwise, such insurance for Subcontractors must be included within Contractor's insurance policies.

ARTICLE 6

INDEMNIFICATION. The Contractor shall secure, defend, protect, hold harmless and indemnify the (Owner, Construction Manager, Architect) and any of their respective agents, servants and employees against any liability, loss, claims, demands, suits, costs, fees and expenses whatsoever arising from bodily injury, sickness, disease (including death resulting there from), of any persons, or damage or destruction of any property, including loss of use, arising out of or in connection with the performance of any work relating to this Contract, including extra work assigned to the Contractor, based upon any act or omission, negligent or otherwise, of (a) the Contractor or any of its agents, employees or servants, (b) any subcontractor, supplier or material men of the Contractor or any agents, employees, or servants thereof, (c) any other person or persons.

The obligations of indemnification contained herein shall exclude only those matters in which the claim arises out of the sole negligence of the (Owner, Construction Manager, Architect) or any of their respective agents, employees or servants.

ARTICLE 7

WARRANTY. Contractor warrants its work against all deficiencies and defects in material and/or workmanship and agrees to satisfy same without cost to Owner for a period of one (1) year from the date of Substantial Completion of the Project or per Contract Documents, whichever is longer.

ARTICLE 8

SAFETY. The prevention of accidents on or in the vicinity of its Work is the Contractor's responsibility, even if Owner establishes a safety program implementing safety measures, policies, and standards conforming to those required or recommended by governmental and quasi-governmental authorities having
jurisdiction and by the Owner, including, but not limited to, requirements imposed by the Contract Documents. Contractor shall comply with the reasonable recommendations or insurance companies having an interest in the Project, and shall stop any part of the Work in which Owner deems unsafe until corrective measures satisfactory to contractor have been taken. Owner's failure to stop Contractor's unsafe practices shall not relieve Contractor of the responsibility there for. Contractor shall notify Owner immediately following any accident and promptly confirm the notice in writing.

A detailed written report shall be furnished if requested by the Owner. Contractor shall indemnify Owner for fines, damages or expenses incurred by the Owner because of the Contractor's failure to comply with safety requirements any amounts due or to become due the Contractor. The Contractor shall satisfy itself as to the safety of any facility, equipment or conveyances placed on the project by the Owner when used by the Contractor, and shall assume the entire responsibility for liability for any bodily injury (including death) to any person or of injury to and property occasioned by such use.

ARTICLE 9

CLEANUP. The Contractor shall follow the Owner's cleanup and safety directions, and (a) at all times keep the building and premises free from debris and unsafe conditions resulting from the Contractor's Work; and (b) broom clean each work area prior to discontinuing work in the same. If the Contractor fails to immediately commence compliance with clean up duties within twenty-four hours after written notification from the Owner of noncompliance, the Owner may implement such cleanup measures without further notice and deduct the cost thereof from any amounts due or to become due the Contractor.

ARTICLE 10

INITIAL DISPUTE RESOLUTION PROCESS. If a dispute arises out of or relates to this Agreement or its breach, the Parties shall endeavor to settle the dispute first through direct discussions. If the dispute cannot be settled through direct discussions, the Parties shall endeavor to settle the dispute by mediation
under the current Construction Industry Mediation Rules of the American Arbitration Association before recourse to any binding dispute resolution procedures.

BINDING DISPUTE RESOLUTION. If the matter is unresolved after submission of the matter to mediation, the Contractor and Owner shall submit the matter to arbitration using the current Construction Industry Arbitration Rules of the American Arbitration Association or the Parties may mutually agree to select another set of arbitration rules. The administration of the arbitration shall be as mutually agreed by the Parties. The costs of any binding dispute resolution procedures shall be borne by the non-prevailing Party, as determined by the adjudicator of the dispute. The venue of any binding dispute resolution procedure shall be the location of the Project, unless the Parties agree on a mutually convenient location.

ARTICLE 11

Liquidated damages may apply at $100.00 per calendar day for each day beyond the scheduled completion date. The Housing Authority will consider explanatory information if it provides a valid reason for delays in schedule and may choose to waive liquidated damages if deemed applicable.

ARTICLE 12

The Bidder certifies by bid submission that it is not included on the list created pursuant to Tenn. Code Ann. § 12-12-106 of the Iran Divestment Act.

ARTICLE 13

Contractor will, in providing labor for the Project, comply with the provisions of the Tennessee Lawful Employment Act, including without limitation maintaining and making available for inspection by Contractor and Owner, as they may deem necessary, appropriate Form l-9's for all employees assigned to the
Project. Contractor must not knowingly utilize the services of illegal immigrants in the performance of a contract for good or services.

SPECIAL CONDITIONS:

  1. Owner - Johnson City Housing Authority enforces a zero tolerance Drug Free Workplace. Contractors are required to also comply accordingly.
  2. The Contractor shall furnish all equipment, small tools, and scaffolding required to perform services stated in this Contract.
  3. All state and local permits are a part of this Contract and shall be furnished by the Contractor.
  4. Contractor is responsible for temporary toilet facilities, temporary power and water however JCHA may provide such items if readily available from vacant units.
  5. Time is of the essence in this contract. Any penalties assessed, as a result of time delays on this project will be passed on to the Contractor or Subcontractors responsible for the delays and the completion of this Contract.
  6. Certificates of insurance and W-9 form must be in Owners possession before any work begins.
  7. Invoices may be submitted monthly for work properly performed and/or at project completion. Retainage will be applicable if deemed necessary by owner.
  8. Before work begins, and in order for the first application for payment to be processed, the contractor must have furnished:
    1. Insurance Certificate's in accordance with Article 5 regarding:
      1. General Liability
      2. Comprehensive Automobile Liability
      3. Worker's Compensation

        Limits shall be in the amount specified in the general conditions of the contract between the owner and contractor.
    2. Performance and payment bonds, if required, on the face of the Contract.
    3. Contractor's application for payment.
      1. Form of application supplied by Owner - Johnson City Housing Authority unless approved otherwise by owner.
      2. In the event the contract amount exceeds $10,000, the approved breakdown schedule of values showing various materials by type, identifying stored materials, and/or segments of the work totaling the full amount of the contract may be required by owner. The schedule of values shall include a line item value for preparation of operation and Maintenance Manuals and As-Built Drawings if applicable as determined by owner.
    4. Safety Data Sheet (SOS) for material placed on the job during the current month and those expected within the next month as applicable.
    5. Signed acknowledgement copy of the contract.
    6. Contractor to furnish a copy of business license and/or contractor's license as applicable.
  9. Owner - Johnson City Housing Authority's Project Managers' are Adam Warren and Dwight Harrell.
  10. No extras will be accepted unless covered by a fully executed Change Order to this contract.
  11. All contractors shall comply with OSHA safety requirements. Any contractor OSHA violation fee is to be paid by contractor.
  12. Shop drawings and submittals shall be submitted within 3 weeks of receipt of the contract in order to meet the construction progress schedule, if applicable.
  13. All correspondence, instruction, questions, etc. shall be sent through Owner - Johnson City Housing Authority.
  14. The project schedule is based on a 5-day work week at 8 hours per day, however extended days and/or hours are permitted (and maybe necessary) with Owner - Johnson City Housing Authority's approval. All contractors are required to adhere to project work schedule.
  15. Project Meetings: Project Manager may hold periodic project meetings to discuss applicable scope of work and/or progress with applicable contractors. Meeting schedules will be announced in advance and Project Superintendents will be expected to attend.
  16. Comply with Executive Order 11246 regarding Equal Employment Opportunity
  17. Comply with a Drug-Free Workplace in accordance with Federal and/or State guidelines And provide certification through contract signature or other forms, as provided by Housing Authority.
  18. Comply with the latest building codes, state and federal laws, relative to public works contracts including the American with Disabilities Act.
  19. Comply with Section 3 of the HUD act of 1968 and encourage utilization of Minority and Women Business Enterprises as feasible.

SECTION 5 - NOTICE TO BIDDERS

In a sealed 10" x 13" envelope, clearly marked with the Outer Bid Envelope Information (Section 6) provided, each bidder is to complete and provide the
following:

  1. Bid / Price Form (SECTION 2). Information is to be filled in on all pages of this Form.
  2. A completed Representations, Certifications, and Other Statements of Bidders (form HUD 5369-A), (SECTION 7).
  3. Bid Bond for bids over $100,000 (5% of the total Contract Amount) **Note** Bid bonds cannot be business or personal checks.
  4. Current Certificates of Insurance for Workman's Compensation, Liability, and Automobile coverage.
  5. A signed "Non-Collusive Affidavit" form (SECTION 8).

NOTE: Failure to provide the above-listed documents, properly executed, may render the bid non-responsive and a contract may not be awarded.

All bidders must be licensed Contractors in the State of Tennessee as required by the Contractors' Licensing Act of 1994 (TCA Title 62, Chapter 6), as revised. The sealed envelope containing the bid must provide the following information: The Contractor's name, address, license number, expiration date, and license classification. Failure of any bidder to comply therewith may void such bid. See "Outer Bid Envelope Information" within this packet.


SECTION 6 - OUTER BID ENVELOPE INFORMATION

Bid Documents
for
Johnson City Housing Authority
Johnson City, Tennessee
INVITATION FOR BID:
Fairview Demolition (26 Buildings)
Bid Opening:
11/23/26 / 2:00 p.m. EST

Bidder's Company Name
Bidder's Address
State Contractor's License Number
Classification
Expiration Date

Note: This page will be furnished to each bidder and shall be taped to the bid envelope. All blanks to be filled in.


SECTION 7 - Representations, Certifications, and Other Statements of Bidders (form HUD-5369-A) (RETURN WITH BID)

HUD-5369 incorporated by reference to www.hud.gov

IFB: Fairview Demolition (26 Buildings)


SECTION 8 - Non-Collusive Affidavit (Return with Bid) 

For the Non-Collusive Affidavit form, please contact us or pick up a copy at our office main office located at 901 Pardee St, Johnson City, TN 37601, during regular office hours.


SECTION 9 - Wage Determination
(subject to change - currently awaiting 2026 update from Department of Labor

IFB: Fairview Demolition (26 Buildings)

U.S. Department of Labor Wage and Hour Division, Washington, DC 20210

September 24, 2025

Alfreida S. Doe
U.S. HUD Region IV
Five Points Plaza Building
40 Marietta Street,
Atlanta, GA 30303
[email protected] 
[email protected] 

RE: Project/Contract No: 25-038 Fairview Apartments
Wage Decision No: TN20240026-Mod-0
Location: Washington County, Tennessee
WHD No: FY25- 37099

Dear Alfreida Doe:

This is in response to your request proposing the addition of classifications and wage rates to the
above wage decision in accordance with 29 CFR 5.5(a)(l)(iii).

The proposed additional classifications and wage rates are:

Proposed Classification:

  • Painter
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Floor Installer
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Drywall Installer
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Drywall Finisher
    • Proposed Basic Hourly Rate: $18.25
    • Proposed Fringe Benefits: $0.00
  • HV AC Mechanical Technician
    • Proposed Basic Hourly Rate: $18.25
    • Proposed Fringe Benefits: $0.00
  • Abatement Worker
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Demolition Worker
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Pipefitter
    • Proposed Basic Hourly Rate: $20.00
    • Proposed Fringe Benefits: $0.00
  • Communications Technician
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • HV AC Duct Technician
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Truck Driver l and 2 axles
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Truck Driver 3 or axles
    • Proposed Basic Hourly Rate: $18.25
    • Proposed Fringe Benefits: $0.00
  • Excavator Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Track hoe Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Dozer Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • End Loader Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Grading Compactor
    • Proposed Basic Hourly Rate: $18.25
    • Proposed Fringe Benefits: $0.00
  • Off Road Hauler
    • Proposed Basic Hourly Rate: $18.25
    • Proposed Fringe Benefits: $0.00
  • Grader
    • Proposed Basic Hourly Rate: $18.25
    • Proposed Fringe Benefits: $0.00
  • Crane Operator
    • Proposed Basic Hourly Rate: $18.25
    • Proposed Fringe Benefits: $0.00
  • Paver Operator
    • Proposed Basic Hourly Rate:$17.75
    • Proposed Fringe Benefits: $0.00
  • Spreader Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Milling Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Bobcat Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Skid Steer Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Tractor Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Roller Operator
    • Proposed Basic Hourly Rate: $17.75
    • Proposed Fringe Benefits: $0.00
  • Blaster
    • Proposed Basic Hourly Rate: $20.00
    • Proposed Fringe Benefits: $0.00
  • Ironworker
    • Proposed Basic Hourly Rate: $18.25
    • Proposed Fringe Benefits: $0.00

Your requested classifications and wage rates are approved and conformed to wage determination number TN20240026 Mod 0. The conformed wage rate shall be paid to all workers performing work in this classification under this contract from the first day on which work is performed.

Your request has been conformed consistent with All Agency Memorandum 213 & 233 (SAM.gov I Wage Determinations) which describes the conformance process in detail. For additional guidance, please follow the link WHD Davis Bacon WD Conformance Request Guide, Sep. 2021. This guide will provide relevant information regarding the conformance process and wage determinations in general. Any requests for appeal of the conformance decision must be made within thirty (30) days from the date of this letter. Please email the appeal letter to [email protected].

If you have any questions or concerns regarding this conformance request, please contact Chiquita Rhodes via email at [email protected].

Sincerely,
Carola Diaz, Section Chief
Branch of Construction Wage
Determinations (202) 655-0971
[email protected]

C.c. Mark S. Markland, Johnson City Housing Authority. [email protected] 

Click here to view the Wage Determination (General Decision Number: TN20260026 05/18/2026).


SECTION 10 - Site Map

IFB: Fairview Demolition (26 Buildings) 

Map of all Fairview buildings.